HQ Building Work Progress Page
badge


arrow Click buttons for section info.

Welcome to the latest news about the upgrade project at our HQ Building in Wroxham.

Our HQ building in Wroxham was opened in 1987 after a huge fund raising effort. It has served us well since that time and a lot of Scouting has been done there. However, since that time, the numbers of young people in the Group has grown a lot, and also, 21st Century expectations of what a building should provide have moved on too. Because of this, we have decided that the building needs an upgrade and so work on the building is now under way with a planned completion date of the end of September 2024.

Improvements to the building include:

New toilets and showers.
A larger main hall with a new higher roof.
A double height extension with extra meeting space and storage.
A climbing wall.
An outside covered area.
Additional car parking.
A "Chill out zone".

Planning permission was granted at the end of April 2023 and we have secured the necessary grant funding. For a Press Release about the Grant, Click Here.
building HQ
Scouts building the HQ in 1987

This is an artist's impression of what the new building will look like. Sunny Petch did the artwork.

new
                  building


Building work began in November 2023 in rather wet conditions for doing groundworks.

Work starts

7th Dec Update.
Work has started on site and fences have been put up. Currently, the diggers are in preparing the ground works.

footings
trailer
digger
swampy

Update - 17th Dec 2023

Foundations
The Foundations of the rear extension are progressing well.

Update - 9th January 2024

The Christmas break is now over and work is again progressing on site.


front
The Foundations of the front extension are complete and the drains are being worked on.

rear ext
The back extension is up to DPC level and the big holes are filled in

Update - 15th Jan 2024

side
The edge of the field is landscaped ready for the side cover
fire circle
The area round the camp fire circle is landscaped

The plan for the rest of January is to complete the ground works over the whole site and to get ready for the building phase.

Update 4th Feb


Front extension
Work has started on the front extension

Groundworks are now nearly complete with the current focus being on the new car park at the back of the building. The base for and the path to the new Annexe are completed.

Update 13th Feb

rear extn
The rear extension and car park are progressing

front
The front extension is also growing

new path
The new wheelchair friendly path is complete

base for annexe
The base for the chill out zone is in place

Update 24th Feb

inside
kitchen
hall
hatch

Inside the old building with everything stripped out ready for the roof to be removed.


Building work update 28th Feb

The building is now covered with scaffolding and the old roof is being removed. The base for the new car park is complete.

roof removal

car park base

scaffolding

skip


Building work update 4th March

Roof gone
The roof has been removed and there are skips everywhere

back view
View from the field side. Demolition work still in progress

gable demolished
The gable end is being demolished. This will be replaced with timber stud.

inside
Inside with no roof

looking bigger
Lots of demolition rubble

view from hatch
View from the old kitchen hatch. This will be there in the new building.

back view inside
The space inside already looks a lot bigger with the back rooms demolished and the ceiling gone.

Building work update 8th March

no walls
The old offices have been removed and now you can see how big the new hall is going to be.

offices removed
The next stage is fitting the steels which will support the new roof and building the new outside walls

side view
This is the most demolished stage. The building will start to grow from here.

Building work update 12th March

Blocks
Blocks are stacked ready for building the walls. Full scaffolding will follow.

Tarmac
Porous tarmac is laid

Roller
The roller gets the car park nice and flat.

Building work update 26th March

The work is coming to a complicated stage where the side walls and supports for the roof have to be got right.

plans
Experts discuss the plans

calculations
Calculations are done.

Building Work Update 11th April

The view from the scaffolding:

from scaffolding
The side walls are now being built

looks big
Blocks are stacked ready for construction of the walls

Experts
Phil (builder) explains the details to Matt (QS) and Roger (Architect)

Chill out zone construction work April 24


The Chill out Zone or Annexe is a kit building. It was built by Scout Volunteers and the Scouts themselves. It is very important for the young people of the Group to take part in the construction of the new HQ. They specified what was wanted and it is good to be hands on building part of it.

base
The wooden base is held together with loads of screws

posts
These posts support the walls and roof

panels
Now the wall panels go in

more panels

walls

Scouts help
Young people help with the construction. They built the lintel and it is staying up well.

doors
The door frame goes in.

roof panels
Those roof panels are heavy, but with a good team they are no problem.

roof on
The roof is secured to the walls

terry
Those long screws hold the roof on. Terry in action with the impact driver.

roof
The last panel fits perfectly

terry and jody
The last roof screws go in

after 2 days
After 2 days it is looking like a complete job. There is still work to do but that is for another weekend.


Building Work Update 24th April

After another weekend of building, our Scout volunteer team have almost got the Annexe finished.

workers

Annexe

roof delivered
Roof parts and joists are delivered to site

internal blockwork
Despite the bad weather, the internal block work is progressing

Building Work Update 10th May


Walls
Block work and steel work progressing on the main hall

office
The new toilets and showers under construction

office
The 2 story offices extension is up to the first floor.


Building Work Update 21st May

The block work in the walls is getting higher and is almost up to roof level. New floor beams go in for the loft storage area above the kitchen and toilets.

view from scaffolding
You can really see how much higher the hall is going to be and what a great space it is.

Building Work Update 11th June

Rain has been causing all sorts of problems for the building team. It really has been a wet spring so far. Despite this, lots of progress has been made. The walls are completed apart from the gable ends and these are nearly done. The scaffolding has been extended and the roof is taking shape.

view from the road
The view from the gate. The new size of the building is now clear.

inside huge and
                                                wet
The inside view shows just how much bigger the space is and how much rain there has been.

outside
The roof over the upstairs room is being built under threatening skies

from scaffolding
The scaffolding is in place to allow the vaulted roof over the hall to be assembled.

shows roof windows
The roof structure over the loft shows where the Velux windows will be fitted.

Roger
Roger the Architect inspecting progress

upstairs room roof
Getting ready for the back roof and gable.


Building Work Update 29th June

At last some decent weather. Warm sunshine has brought real progress:

roof and render
All the roof beams are in place and the lower walls are rendered

inside render
Render going on the internal walls. You can see above the barn door hatch to the loft.

roof
The gable ends are complete and insulation is being fitted to the roof.

upstairs room
Looking through the window into the upstairs room

loft
The loft storage space can be seen between the beams

Building Work Update 11th July

We are watertight and work can begin inside:

side
                                                    view
The roof is battened and temporary windows fitted

battens
Ready for tiles

floor
                                                          ready
The floor is ready for pouring the screed
stairs
Experts discuss the metal stairs

Further Update 12th July

The floor screeds are poured and the front and back of the building. They will dry over the weekend and will look fantastic.

screed
Downstairs office

stairwell
Stairwell and back door

hallway
Front entrance hallway, kitchen and toilets


Building Work Update 20th July

Good weather continues to bring good progress. Our volunteer team has been working over the weekend to get the Annexe building ready for second fix electrics. The electrician and the plumber are now working inside the main building and the roof is tiled.

tiled
The roof is now fully tiled and looks great with its Velux windows.

steels
The steel work is now in place for the covered verandah along the side of the building. The roof will go on when the scaffolding is taken down.

Annexe
The Annexe is really looking finished now.

ready for 2nd fix
The internal walls and floor have been fitted ready for the 2nd fix electrics.

good space
Still a bit of work to do but you can see what a good space this is going to be.

Building Work Update 30th July

The good weather has continued and the building is watertight so lots of work is going on inside as well as outside.

inside
The internal scaffolding is still in place while the ceiling is plastered and painted

solar panels
The solar panels have been fitted on the roof

inverters
The inverter for the solar system is installed in the loft
wires

There are wires, water pipes and an RSJ installed in the roof above the toilets.

kitchen
The kitchen has been delivered but it is still in flatpack form.

kitchen
Cables and pipes are fitted in the kitchen room.
cables
More cables in the front hallway

scaffolding
The scaffolding is lowered so that the cedar cladding can be fitted. The roof is now complete.


Building Work Update 5th August

The good weather is holding and work has begun on the external cedar cladding. Inside the floor has been poured in the main hall and the internal scaffolding has been removed. This means that the size of the main hall is revealed for the first time. It certainly looks good. Electrical work inside continues. The doors and windows are due next week.

cedar

Above - Cedar cladding the rear of the building.

Right- The ceiling is ready except for the lights
inside
                                                          roof


side
                                                          battening
The side is battened ready for cedar cladding

back render
Preparing the area under the verandah for rendering

Inside
The new floor is down and the full size and height of the main hall is now visible.

reverse view
Looking down the main hall towards the rear of the building. The end wall will soon have the climbing wall fitted to it. The Velux windows in the roof will bring lots of light into the building. The lower block work on the left and right will be painted.

scaffolding removed
Scaffolding is being removed at the front.

front cedar
Cedar cladding is complete on the front of the building. We are using boards of 3 different widths to give this effect.

Building Work Update 19th August

Cedar cladding is complete. The side covered area is almost finished. The kitchen is in. The climbing wall installation is complete and the doors and windows are in. There is still a lot to do but progress is really good.

climbing wall
Looking towards the back of the hall and the new climbing wall.

kitchen end
Looking towards the front. The floor has been sanded and rendering work is in progress

solar
The solar electrics are in place

loft hatch
The loft hatch doors still need their safety rails
view from
                                                          loft
Work continues in the loft

loft view
The view from the loft hatch

cladding
The cedar cladding is complete and looking good

covered side
The roof of the covered side area is being battened and tiled.

Building Work Update 28th August

The scaffolding has been removed and now you can see what the final building will look like. There is still work to be done outside, but the rendering and cedar cladding are looking fantastic. Inside, the walls are being rendered and plastered.

outside
                                                          front
Front view on a sunny day. The cedar cladding looks great.

front corner
There are still ground works to do and all those cables show that the 2nd fix electrics has not been done yet.

kitchen wall
Rendering work on the end wall. Below the horizontal line, the render top coat will be blue.

hallway
Rendering the entrance hall
stairwell
Plastering the stairwell.

rear view
The back of the building with the scaffolding gone. Doors, windows and cladding all looking good.

rear right corner
The covered area at the side is complete. There are still ground works to be done in this area.

Building Work Update 2nd September

The concrete paths round the building are being installed. Parallel Fabrications are installing the metal stairs. Rendering and plastering work continues throughout the building.

base at back
Preparing for the concrete floor under the side covered area

Inside
Inside the main hall

digger
Digger leveling the ballast

disable
                                                          toilet
Rendering the accessible toilet
toilet
                                                          rendering
Rendering the toilets
hatch rails
Ready for the loft hatch railings

stairs fitters
Parallel Fabrications start getting the stairs ready for installation

half landing
The half landing looks like a sort of table at first. There will be storage underneath.

stairs
Now the stairs start assembly
stairs
Looks like the measurements were right.

stair
stairs
All you have to do is sort out the right bits

stairs
Some of the stair treads are now in place

office
Small office now plastered. As you can see, this room is where all the telecomms cables go.
loft hatch
The electric loft hatch is now in place. The ladder will descend at the touch of a button.

kitchen hatch
View from the kitchen hatch


Building Work Update 12th September

The work outside the building is being completed. The concrete surround is in place and the temporary buildings removed. The grass has been cut and graded.
Inside the decorators are busy painting, The main walls are white with navy blue at the bottom. The stairs and the storage space under them are complete. The section cupboards in the hallway are under construction.
The target for completion remains the end of the month.

concrete
The lean to verandah is finished and the concrete surround is poured

field side
The field side is graded to the concrete

entrance
The front entrance slope is in place and the temporary buildings are gone. The wall will have a handrail.

kitchen hatch
The lower parts of the walls will be navy blue

undercoat
This is just the undercoat for the blue render

walls white
The side walls being painted

steels blue
The steel beams will be blue

discussion
Matt (QS), Phil (builder) and Roger (Architect) discussing
loft
                                                          rail
Safety railings in the loft area
cupboards
Cupboards under construction
small
                                                          downstairs
                                                          office
Small downstairs room decorated
small
                                                          upstairs
Small upstairs room being decorated
painting
                                                          stairs
Painting above the stairs

office
Office is decorated

upstairs room being
                                                          decorated
The large upstairs room is decorated

Building Work Extra Update 13th September



A real milestone has been reached today. It has been such a long time since we had electrical power in the building. Now, at last, the power has been connected.

We also have internet connected thanks to Openreach.

One of the fun things that this means is that we now have our CCTV cameras working and we can watch what is happening on site remotely in real time. This will be an interesting watch as the building work progresses.

It also means that our remotely monitored alarm system is up and running which considerably increases the security of the site.

Decorating work is progressing well inside the building and the car park has been leveled and landscaped ready for new surfacing.
TV
Building Work Update 24th September

The building work is nearly complete. Electrical work continues along with plumbing and decorating. Outside the car park has new gravel and the land has been graded and leveled.

car park
The car park is looking good. Still need to fix handrails by the front door.

loft
This is inside the loft storage area.

electric
                                                          stairs
The loft ladder is electric remote controlled
ladder
                                                          folded
It folds up and closes its own hatch
basins
Wash basins going in.
lights
Lights are fitted to the roof.

climbing
                                                          wall
The climbing wall has had 2 coats of fire proof paint

outside
Outside all the levels are sorted out.

air source
The air source heat pump is in place.

painted
The walls at the kitchen end are decorated and completed

lights
The hall lights are in and on.


Building Work Update 2nd October

The building is virtually completed now. We are just waiting for the screed to be dry enough in the toilets to put the floor down and for the metal handrails to arrive. With a bit of luck we will be completed in a week or so. It is better to wait and get the job done properly than to rush to completion, but as you can see, we will soon be able to move into the new building.

car park
                                                          view
From the car park with the outside lights on.

back
Back view

side covere
Under the side cover. There will be a couple of washing up sinks to fit at the far end.

inside
Looking down the hall towards the climbing wall. The floor is still being worked on.

kitchen end
Looking back towards the kitchen

upstairs
The upstairs rooms have floors
shower
The showers are in

annexe
Inside the annexe. It now has power, alarm and CCTV. There is a little bit of finishing off to do in here. The walls need painting and the floor will have a vinyl covering.

Building Work Update 1st November

The building is virtually completed now. It will be handed over to us by the builder in the middle of November and we expect to start meeting there on the 18th of November onwards.

Thank you to everyone who has helped to make this possible.

car park
                                                          view


Building Work Update 15th November

It is Handover Day

The building is finished, the builder has left the site and it is now ours. Here are some photographs of the building as it was handed over to us.

The building looks really crisp and clean and it is a credit to the fantastic workmanship of Phil Drake and the PD Drake building team. They have done a really wonderful, quality job and we are so happy with the result. What's more, they have been an absolute pleasure to work with and have dealt with all the problems along the way with a really positive, "can do" attitude.If you are looking for a quality builder, well here is the link you need.

Thank you also to Roger Connolly our Architect and Project Manager, to Matt Woollard our Quantity Surveyor, to Emma Macklin who provided the funds and to everyone who has helped to make this possible.

So, take a look at the pictures on handover day. You will probably never see it so clean or so empty again:

accessible
                                                          toilet
The accessible toilet and shower is complete. It is the floor in the toilets that has been delaying the opening of the building.

ladies
New cubicles in the female toilet

sinks
A nice clean row of new sinks

gents
The male toilet is completed also

kitchen
A brand new kitchen. That notice board on the drainer is going outside by the door.

kitchen
                                                          hatch
A view of the kitchen through the hatch

hall
The floor in the main hall has had a final coat of paint and the climbing wall has been inspected.

hall
Looking back towards the kitchen

upstairs
The upstairs meeting room has some new chairs (well - new to us anyway)

cupboards
New storage cupboards for meeting equipment.

notice
As you can see, the building was funded by the UK Government.

rainbow
                                                          pegs
The coat pegs have a rainbow backing to protect the wall.


Back to Newsletter